Site Progress Summary Concrete pouring at Level 21 completed. Decking work ongoing at Level 22. Structural vertical elements between Levels 21–22 in progress. Mechanical and HVAC installation ongoing from Basement 1 upwards. Electrical work: wire pulling in progress at Level 19. Curtain wall installation ongoing at Level 8 and the south elevation from Level 4 […]
Author: Concord Sky
Concord SKY Project Construction Status-September 2025
19th floor concrete pouring completed. 20th floor decking ongoing. Structural vertical elements between L19 and L20 ongoing. Mechanical and HVAC work at B01 and up ongoing. Electrical pulling wires on level 17 ongoing. Curtain wall installation at level 7 ongoing. Stairs railing installation ongoing from ground floor up to level 14. Services rooms painting below […]
Concord SKY Project Construction Status-August 2025
– 18th floor concrete pouring completed.– Structural vertical elements between L18 & L19 ongoing.– Mechanical and HVAC work B01 and up ongoing.– Electrical pulling wires on L16 ongoing.– Curtain wall installation on L03, L04, and L05 ongoing.– Escalators installation completed (except the escalators railings).– Railing installation up to L14 ongoing. – Painting at B02, B01 […]
Concord SKY Project Construction Status-July 2025
16th floor concrete pouring completed. 17th floor concrete slab pouring and forming ongoing. Structural vertical elements between L17 & L18 ongoing. Mechanical and HVAC work up to L09 ongoing. Electrical pulling wires on L14 ongoing. Curtain wall installation on L03, L04, and L05 ongoing. Escalators installation ongoing. Railing installation from B05 to B01M completed and […]
Concord SKY Project Construction Status-June 2025
15th floor concrete slab completed. 16th floor concrete slab pouring and forming ongoing. Structural vertical elements between 15th to 16th floors on going. MEP works up to level 9 is ongoing. Curtain wall installation ongoing at 3rd and 4th floors. Canopy out riggers installation at level 4 completed.
Concord SKY Project-Construction Status-May 2025
13th floor concrete slab completed. 14th floor concrete slab pouring and forming ongoing. Structural vertical elements between 13th to 14th floors and 14th to 15th floors are ongoing. MEP works up to level 9 ongoing. Stairs handrails installation completed below ground floor levels. Curtain walls delivery completed for levels 2, 4, 5, 6, 7, and […]
Concord SKY project-Construction Status-April 2025
11th floor concrete slab completed. 12th floor concrete pouring and forming ongoing. Structural vertical elements between 12th and 13th floors are on going. MEP works ongoing. From basement 05 to ground floor level stairs railing installation on going. Levels 2, 4, 5 and 6 curtain wall delivery on going.
Concord SKY Project-Construction Status-February 2025
10th floor concrete slab completed. Structural vertical elements between 10th and 11th floor concrete pouring ongoing. 11th floor slab framing including the swimming pool and hot tub ongoing. Block work activity including the hollow metal door frames from B05 to B01 mezzanine ongoing.
Concord SKY Project-Construction Status-January 2025
10th floor slab concrete pouring ongoing. Verticals between 10th & 11th floor concrete pouring ongoing. HVAC & MEP activities ongoing. Block work activities B05 to B01M ongoing.
Concord SKY Project Construction Status-December 2024
9th floor slab concrete pouring completed. Verticals between 9th & 10th floor concrete pouring on going. 10th floor forming ongoing. HVAC & MEP activities on going. Block work activities below grade on going. Temporary/Permanent gas connection completed.