16th floor concrete pouring completed. 17th floor concrete slab pouring and forming ongoing. Structural vertical elements between L17 & L18 ongoing. Mechanical and HVAC work up to L09 ongoing. Electrical pulling wires on L14 ongoing. Curtain wall installation on L03, L04, and L05 ongoing. Escalators installation ongoing. Railing installation from B05 to B01M completed and […]
Author: Concord Sky
Concord SKY Project Construction Status-June 2025
15th floor concrete slab completed. 16th floor concrete slab pouring and forming ongoing. Structural vertical elements between 15th to 16th floors on going. MEP works up to level 9 is ongoing. Curtain wall installation ongoing at 3rd and 4th floors. Canopy out riggers installation at level 4 completed.
Concord SKY Project-Construction Status-May 2025
13th floor concrete slab completed. 14th floor concrete slab pouring and forming ongoing. Structural vertical elements between 13th to 14th floors and 14th to 15th floors are ongoing. MEP works up to level 9 ongoing. Stairs handrails installation completed below ground floor levels. Curtain walls delivery completed for levels 2, 4, 5, 6, 7, and […]
Concord SKY project-Construction Status-April 2025
11th floor concrete slab completed. 12th floor concrete pouring and forming ongoing. Structural vertical elements between 12th and 13th floors are on going. MEP works ongoing. From basement 05 to ground floor level stairs railing installation on going. Levels 2, 4, 5 and 6 curtain wall delivery on going.
Concord SKY Project-Construction Status-February 2025
10th floor concrete slab completed. Structural vertical elements between 10th and 11th floor concrete pouring ongoing. 11th floor slab framing including the swimming pool and hot tub ongoing. Block work activity including the hollow metal door frames from B05 to B01 mezzanine ongoing.
Concord SKY Project-Construction Status-January 2025
10th floor slab concrete pouring ongoing. Verticals between 10th & 11th floor concrete pouring ongoing. HVAC & MEP activities ongoing. Block work activities B05 to B01M ongoing.
Concord SKY Project Construction Status-December 2024
9th floor slab concrete pouring completed. Verticals between 9th & 10th floor concrete pouring on going. 10th floor forming ongoing. HVAC & MEP activities on going. Block work activities below grade on going. Temporary/Permanent gas connection completed.
Concord SKY Project Construction Status-October 2024
8th floor concrete pouring and decking activities on going. Verticals between 8th & 9th floor concrete pouring on going. HVAC & MEP activities on going. Block work activity started.
Concord SKY Project Construction Status-September 2024
5th floor concrete pouring and decking ongoing. Verticals between 5th floor and 6th floor concrete pouring ongoing. Temporary king piles/caissons demolition completed.
Concord SKY Project Construction Status-June 2024
Activities: 3rd floor decking and concrete pouring ongoing. 3rd floor to 4th floor verticals ongoing. 4th floor decking on going. Fire fighting sprinklers at B05 completed and BO4 ongoing. Temporary caisson removal tentatively scheduled to start at the mid-July.