Concord SKY Project Construction Report-October2026

·  Concrete forming at level 43 is ongoing.

·  Structural vertical elements for Levels 42–43 are ongoing.

·  L34: Curtain wall installation is ongoing.

.  L35: Balcony railing installation is ongoing.

.  L32: Window wall installation completed.

·  L29: Corridor and demising wall framing ongoing.

·  L26: Two-side boarding installation to demise and corridor walls are ongoing.

·  L20: Floor leveling.

·  L16: Ceiling framing and electrical rough-in are ongoing.

·  L15: Two sides walls boarding and mudding, are ongoing.

.  L15: bath-tub installation ongoing.

.  L13: Tile installation ongoing.

.  L8: kitchen cabinets installation ongoing.

.  Heritage works are ongoing.