· Concrete forming at level 43 is ongoing.
· Structural vertical elements for Levels 42–43 are ongoing.
· L34: Curtain wall installation is ongoing.
. L35: Balcony railing installation is ongoing.
. L32: Window wall installation completed.
· L29: Corridor and demising wall framing ongoing.
· L26: Two-side boarding installation to demise and corridor walls are ongoing.
· L20: Floor leveling.
· L16: Ceiling framing and electrical rough-in are ongoing.
· L15: Two sides walls boarding and mudding, are ongoing.
. L15: bath-tub installation ongoing.
. L13: Tile installation ongoing.
. L8: kitchen cabinets installation ongoing.
. Heritage works are ongoing.