Concord SKY Project Construction Report-May 2026

  • Concrete pouring at level 32 is completed.
  • Structural vertical elements for Levels 32–33 are ongoing.
  • L22 Window wall installation is completed, and curtain wall installation is ongoing.
  • L17-19: Corridor and demising wall framing ongoing.
  • L16: Corridor and demising walls, one side boarding is ongoing.
  • L13-15: Drywall and wall insulation is ongoing.
  • L4, 5 & 9: corridor ceiling tracks installation started.
  • Generator delivered and installed.
  • HVAC installation is ongoing from level B01 upwards.
  • Electrical wire pulling is in progress at level 29.
  • Switchgears and transformers installation is ongoing at basement mezzanine level.