Concord SKY Project Construction Report-July 2026

·  Concrete pouring at level 36 is ongoing.

·  Structural vertical elements for Levels 35–36 are ongoing.

·  L27 curtain wall installation is ongoing.

.  L29 balcony railing installation is ongoing.

.  L24 window wall installation completed.

·  L19-21: Corridor and demising wall framing ongoing.

·  L16: Two-side boarding installation to demise and corridor walls are ongoing.

·  L14&15: Interior wall framing layout is ongoing.

·  L8&9: ceiling framing and electrical rough-in are ongoing.

.  L6: bath-tub installation ongoing.

.  L5-7: drywall sanding and touch-ups are ongoing.

·  HVAC installation is ongoing from level B01 upwards.

·  Electrical wire pulling is in progress at level 33.

·  Switchgears and transformers installation is ongoing at basement mezzanine level.