· Concrete pouring at level 36 is ongoing.
· Structural vertical elements for Levels 35–36 are ongoing.
· L27 curtain wall installation is ongoing.
. L29 balcony railing installation is ongoing.
. L24 window wall installation completed.
· L19-21: Corridor and demising wall framing ongoing.
· L16: Two-side boarding installation to demise and corridor walls are ongoing.
· L14&15: Interior wall framing layout is ongoing.
· L8&9: ceiling framing and electrical rough-in are ongoing.
. L6: bath-tub installation ongoing.
. L5-7: drywall sanding and touch-ups are ongoing.
· HVAC installation is ongoing from level B01 upwards.
· Electrical wire pulling is in progress at level 33.
· Switchgears and transformers installation is ongoing at basement mezzanine level.