Concord SKY Project Construction Status-September 2025

  • 19th floor concrete pouring completed.
  • 20th floor decking ongoing.
  • Structural vertical elements between L19 and L20 ongoing.
  • Mechanical and HVAC work at B01 and up ongoing.
  • Electrical pulling wires on level 17 ongoing.
  • Curtain wall installation at level 7 ongoing.
  • Stairs railing installation ongoing from ground floor up to level 14.
  • Services rooms painting below ground floor completed.

Concord SKY Project Construction Status-August 2025

– 18th floor concrete pouring completed.
– Structural vertical elements between L18 & L19 ongoing.
– Mechanical and HVAC work B01 and up ongoing.
– Electrical pulling wires on L16 ongoing.
– Curtain wall installation on L03, L04, and L05 ongoing.
– Escalators installation completed (except the escalators railings).
– Railing installation up to L14 ongoing.

– Painting at B02, B01 and B01M services rooms completed and on B03 ongoing.

Concord SKY Project Construction Status-July 2025

  1. 16th floor concrete pouring completed.
  2. 17th floor concrete slab pouring and forming ongoing.
  3. Structural vertical elements between L17 & L18 ongoing.
  4. Mechanical and HVAC work up to L09 ongoing.
  5. Electrical pulling wires on L14 ongoing.
  6. Curtain wall installation on L03, L04, and L05 ongoing.
  7. Escalators installation ongoing.
  8. Railing installation from B05 to B01M completed and GF to L09 ongoing.

Concord SKY Project-Construction Status-May 2025

  1. 13th floor concrete slab completed.
  2. 14th floor concrete slab pouring and forming ongoing.
  3. Structural vertical elements between 13th to 14th floors and 14th to 15th floors are ongoing.
  4. MEP works up to level 9 ongoing.
  5. Stairs handrails installation completed below ground floor levels.
  6. Curtain walls delivery completed for levels 2, 4, 5, 6, 7, and 8.
  7. Garbage chute installation ongoing below ground floor levels.