Concord SKY Project Construction Status-July 2025

  1. 16th floor concrete pouring completed.
  2. 17th floor concrete slab pouring and forming ongoing.
  3. Structural vertical elements between L17 & L18 ongoing.
  4. Mechanical and HVAC work up to L09 ongoing.
  5. Electrical pulling wires on L14 ongoing.
  6. Curtain wall installation on L03, L04, and L05 ongoing.
  7. Escalators installation ongoing.
  8. Railing installation from B05 to B01M completed and GF to L09 ongoing.

Concord SKY Project-Construction Status-May 2025

  1. 13th floor concrete slab completed.
  2. 14th floor concrete slab pouring and forming ongoing.
  3. Structural vertical elements between 13th to 14th floors and 14th to 15th floors are ongoing.
  4. MEP works up to level 9 ongoing.
  5. Stairs handrails installation completed below ground floor levels.
  6. Curtain walls delivery completed for levels 2, 4, 5, 6, 7, and 8.
  7. Garbage chute installation ongoing below ground floor levels.