Skip to content

Concord Sky Construction webpage

Concord SKY project-Construction Status-April 2025

  • Post author By Concord Sky
  • Post date April 17, 2025
  • No Comments on Concord SKY project-Construction Status-April 2025
  1. 11th floor concrete slab completed.
  2. 12th floor concrete pouring and forming ongoing.
  3. Structural vertical elements between 12th and 13th floors are on going.
  4. MEP works ongoing.
  5. From basement 05 to ground floor level stairs railing installation on going.
  6. Levels 2, 4, 5 and 6 curtain wall delivery on going.

Concord SKY Project-Construction Status-February 2025

  • Post author By Concord Sky
  • Post date February 27, 2025
  • No Comments on Concord SKY Project-Construction Status-February 2025
  1. 10th floor concrete slab completed.
  2. Structural vertical elements between 10th and 11th floor concrete pouring ongoing.
  3. 11th floor slab framing including the swimming pool and hot tub ongoing.
  4. Block work activity including the hollow metal door frames from B05 to B01 mezzanine ongoing.

Concord SKY Project-Construction Status-January 2025

  • Post author By Concord Sky
  • Post date January 30, 2025
  • No Comments on Concord SKY Project-Construction Status-January 2025
  1. 10th floor slab concrete pouring ongoing.
  2. Verticals between 10th & 11th floor concrete pouring ongoing.
  3. HVAC & MEP activities ongoing.
  4. Block work activities B05 to B01M ongoing.

Concord SKY Project Construction Status-December 2024

  • Post author By Concord Sky
  • Post date December 12, 2024
  • No Comments on Concord SKY Project Construction Status-December 2024
  1. 9th floor slab concrete pouring completed.
  2. Verticals between 9th & 10th floor concrete pouring on going.
  3. 10th floor forming ongoing.
  4. HVAC & MEP activities on going.
  5. Block work activities below grade on going.
  6. Temporary/Permanent gas connection completed.

Concord SKY Project Construction Status-October 2024

  • Post author By Concord Sky
  • Post date October 31, 2024
  • No Comments on Concord SKY Project Construction Status-October 2024
  1. 8th floor concrete pouring and decking activities on going.
  2. Verticals between 8th & 9th floor concrete pouring on going.
  3. HVAC & MEP activities on going.
  4. Block work activity started.

Concord SKY Project Construction Status-September 2024

  • Post author By Concord Sky
  • Post date September 4, 2024
  • No Comments on Concord SKY Project Construction Status-September 2024
  1. 5th floor concrete pouring and decking ongoing.
  2. Verticals between 5th floor and 6th floor concrete pouring ongoing.
  3. Temporary king piles/caissons demolition completed.

Concord SKY Project Construction Status-June 2024

  • Post author By Concord Sky
  • Post date June 27, 2024
  • No Comments on Concord SKY Project Construction Status-June 2024

Activities:

  1. 3rd floor decking and concrete pouring ongoing.
  2. 3rd floor to 4th floor verticals ongoing.
  3. 4th floor decking on going.
  4. Fire fighting sprinklers at B05 completed and BO4 ongoing.
  5. Temporary caisson removal tentatively scheduled to start at the mid-July.

Concord SKY Project Construction Status-May 2024

  • Post author By Concord Sky
  • Post date May 16, 2024
  • No Comments on Concord SKY Project Construction Status-May 2024
  • 2nd to 3rd floor structural vertical elements are ongoing (almost finished)
  • 3rd floor decking and concrete pouring ongoing.
default
default
default

Concord SKY project construction status – April 2024

  • Post author By Concord Sky
  • Post date April 10, 2024
  • No Comments on Concord SKY project construction status – April 2024
  • Ground floor vertical structural elements to 2nd floor are completed.
  • Ground floor mezzanine and 2nd floor decking and concrete pour are ongoing.
  • 2nd floor vertical structural elements are ongoing.
  • Please refer to the updated photos below.

default
default
default
default

Project Status March 2024

  • Post author By Concord Sky
  • Post date March 14, 2024
  • No Comments on Project Status March 2024

Hi,

Below is a brief of Concord SKY project construction status:

Ground floor structural vertical elements to ground floor mezzanine and to 2nd floor are on going.

Ground floor mezzanine and 2nd Floor decking and concrete pour are ongoing.

2nd floor to 3rd floor south wall forming on going.

Please refer to the attached photos below.

Thank you.


default
default

default
default

Posts navigation

1 2 Older Posts →
© 2025