Skip to content
- 13th floor concrete slab completed.
- 14th floor concrete slab pouring and forming ongoing.
- Structural vertical elements between 13th to 14th floors and 14th to 15th floors are ongoing.
- MEP works up to level 9 ongoing.
- Stairs handrails installation completed below ground floor levels.
- Curtain walls delivery completed for levels 2, 4, 5, 6, 7, and 8.
- Garbage chute installation ongoing below ground floor levels.
- 10th floor concrete slab completed.
- Structural vertical elements between 10th and 11th floor concrete pouring ongoing.
- 11th floor slab framing including the swimming pool and hot tub ongoing.
- Block work activity including the hollow metal door frames from B05 to B01 mezzanine ongoing.
- 10th floor slab concrete pouring ongoing.
- Verticals between 10th & 11th floor concrete pouring ongoing.
- HVAC & MEP activities ongoing.
- Block work activities B05 to B01M ongoing.
- 9th floor slab concrete pouring completed.
- Verticals between 9th & 10th floor concrete pouring on going.
- 10th floor forming ongoing.
- HVAC & MEP activities on going.
- Block work activities below grade on going.
- Temporary/Permanent gas connection completed.
- 8th floor concrete pouring and decking activities on going.
- Verticals between 8th & 9th floor concrete pouring on going.
- HVAC & MEP activities on going.
- Block work activity started.
- 5th floor concrete pouring and decking ongoing.
- Verticals between 5th floor and 6th floor concrete pouring ongoing.
- Temporary king piles/caissons demolition completed.
- 2nd to 3rd floor structural vertical elements are ongoing (almost finished)
- 3rd floor decking and concrete pouring ongoing.
default
default
default