- 9th floor slab concrete pouring completed.
- Verticals between 9th & 10th floor concrete pouring on going.
- 10th floor forming ongoing.
- HVAC & MEP activities on going.
- Block work activities below grade on going.
- Temporary/Permanent gas connection completed.
Concord SKY Project Construction Status-October 2024
- 8th floor concrete pouring and decking activities on going.
- Verticals between 8th & 9th floor concrete pouring on going.
- HVAC & MEP activities on going.
- Block work activity started.
Concord SKY Project Construction Status-September 2024
- 5th floor concrete pouring and decking ongoing.
- Verticals between 5th floor and 6th floor concrete pouring ongoing.
- Temporary king piles/caissons demolition completed.
Concord SKY Project Construction Status-June 2024
Activities:
- 3rd floor decking and concrete pouring ongoing.
- 3rd floor to 4th floor verticals ongoing.
- 4th floor decking on going.
- Fire fighting sprinklers at B05 completed and BO4 ongoing.
- Temporary caisson removal tentatively scheduled to start at the mid-July.
Concord SKY Project Construction Status-May 2024
- 2nd to 3rd floor structural vertical elements are ongoing (almost finished)
- 3rd floor decking and concrete pouring ongoing.
Concord SKY project construction status – April 2024
- Ground floor vertical structural elements to 2nd floor are completed.
- Ground floor mezzanine and 2nd floor decking and concrete pour are ongoing.
- 2nd floor vertical structural elements are ongoing.
- Please refer to the updated photos below.
Project Status March 2024
Hi,
Below is a brief of Concord SKY project construction status:
Ground floor structural vertical elements to ground floor mezzanine and to 2nd floor are on going.
Ground floor mezzanine and 2nd Floor decking and concrete pour are ongoing.
2nd floor to 3rd floor south wall forming on going.
Please refer to the attached photos below.
Thank you.
default
Yonge Street Traffic Control
Beginning this Friday March 15th, Concord Sky will be re-routing the sidewalk on the east side of Yonge Street to allow installation of overhead sidewalk protection. The drawing below shows the extent of the work area. This work is scheduled to take approximately two weeks to complete, with the sidewalk and lane closures re-instated at the end of each working day. Trained traffic personnel will be assigned full time during the closure. Every effort will be made to minimize the disruption.
Ground Floor Slab
Ground Floor slab poured and vertical elements all the way to level 2 are ongoing
Slab on grade has been poured
This is a new update regarding Concord SKY project construction progress , I am welling to announce that slab on grade has been fully poured and all the vertical structural elements between B05 to B04 have been poured as well.