Concord SKY Project Construction Status-September 2025

  • 19th floor concrete pouring completed.
  • 20th floor decking ongoing.
  • Structural vertical elements between L19 and L20 ongoing.
  • Mechanical and HVAC work at B01 and up ongoing.
  • Electrical pulling wires on level 17 ongoing.
  • Curtain wall installation at level 7 ongoing.
  • Stairs railing installation ongoing from ground floor up to level 14.
  • Services rooms painting below ground floor completed.