- 15th floor concrete slab completed.
- 16th floor concrete slab pouring and forming ongoing.
- Structural vertical elements between 15th to 16th floors on going.
- MEP works up to level 9 is ongoing.
- Curtain wall installation ongoing at 3rd and 4th floors.
- Canopy out riggers installation at level 4 completed.