Concord SKY Project Construction Status-July 2025

  1. 16th floor concrete pouring completed.
  2. 17th floor concrete slab pouring and forming ongoing.
  3. Structural vertical elements between L17 & L18 ongoing.
  4. Mechanical and HVAC work up to L09 ongoing.
  5. Electrical pulling wires on L14 ongoing.
  6. Curtain wall installation on L03, L04, and L05 ongoing.
  7. Escalators installation ongoing.
  8. Railing installation from B05 to B01M completed and GF to L09 ongoing.