Concord SKY Project Construction Status-August 2025

– 18th floor concrete pouring completed.
– Structural vertical elements between L18 & L19 ongoing.
– Mechanical and HVAC work B01 and up ongoing.
– Electrical pulling wires on L16 ongoing.
– Curtain wall installation on L03, L04, and L05 ongoing.
– Escalators installation completed (except the escalators railings).
– Railing installation up to L14 ongoing.

– Painting at B02, B01 and B01M services rooms completed and on B03 ongoing.