Concord SKY Project Construction Report-September 2026

·  Concrete forming at level 41 is ongoing.

·  Structural vertical elements for Levels 40–41 are ongoing.

·  L32: curtain wall installation is ongoing.

.  L29: balcony railing installation is ongoing.

.  L29: window wall installation completed.

·  L25: Corridor and demising wall framing ongoing.

·  L22: Two-side boarding installation to demise and corridor walls are ongoing.

·  L17: Floor leveling.

·  L15: ceiling framing and electrical rough-in are ongoing.

.  L14: bath-tub installation ongoing.

.  L8: Tile installation ongoing.

.  L4-6: kitchen cabinets installation ongoing.

.  Heritage works are ongoing.