Concord SKY Project Construction Report-June 2026

·  Concrete pouring at level 34 is ongoing.

·  Structural vertical elements for Levels 34–35 are ongoing.

·  L24 curtain wall installation is ongoing.

·  L19-21: Corridor and demising wall framing ongoing.

·  L18: Corridor and demising walls, one side boarding is ongoing.

·  L15-17: Drywall and wall insulation is ongoing.

·  L4, 5 & 9: corridor ceiling tracks installation ongoing.

·  HVAC installation is ongoing from level B01 upwards.

·  Electrical wire pulling is in progress at level 32.

·  Switchgears and transformers installation is ongoing at basement mezzanine level.