- Concrete pouring at level 29 is completed.
- Structural vertical elements for Levels 29–30 are ongoing.
- Curtain wall installation at Level 18 has been completed, and railing installation has commenced.
- Window wall installation is scheduled to begin next week.
- L4: Interior walls stud installation, corridor boarding, concrete ceiling painting, electrical panels installation, MEP suite rough-ins, and bath-tubs installation are ongoing.
- Levels 5, 6, and 7: Interior wall stud installation is ongoing.
- Levels 8–15: Drywall installation for corridor and demising walls has commenced.
- HVAC installation is ongoing from level B01 upwards.
- Electrical wire pulling is in progress at level 27.
- Switchgears installation is ongoing at basement mezzanine level.