Concord SKY Project Construction Status December 2025

  • Concrete pouring at level 24 is ongoing.
  • Curtain wall installation from level 4 up to at level 9 completed.
  • Corridor and demising wall framing are ongoing on level 4, 5, 6, and 7.
  • Porcelain cladding installation completed up to level 9 of the north elevation.
  • HVAC installation is ongoing from level 2 upwards.
  • Electrical wire pulling in progress at level 22.
  • Permanent lights installation at stair A & B from ground floor up to level 9 is ongoing.
  • Stair railing installation up to level 20 is ongoing.