Concord SKY Project Construction Status-November 2025

  • Concrete pouring at Level 23 is completed
  • Decking work started at level 24
  • Vertical elements between Levels 23–24 is ongoing
  • HVAC installation is ongoing from Level 2 upwards.
  • Electrical: wire pulling in progress at Level 20.
  • Curtain wall installation at Level 9 is ongoing and the south elevation from level 4 to 9.
  • Installation of the exterior porcelain panels at the north elevation started.
  • walls framing at level 4 started.