- Concrete pouring at Level 23 is completed
- Decking work started at level 24
- Vertical elements between Levels 23–24 is ongoing
- HVAC installation is ongoing from Level 2 upwards.
- Electrical: wire pulling in progress at Level 20.
- Curtain wall installation at Level 9 is ongoing and the south elevation from level 4 to 9.
- Installation of the exterior porcelain panels at the north elevation started.
- walls framing at level 4 started.