Concord SKY Project Construction Status-October 2025

Site Progress Summary

  1. Concrete pouring at Level 21 completed.
  2. Decking work ongoing at Level 22.
  3. Structural vertical elements between Levels 21–22 in progress.
  4. Mechanical and HVAC installation ongoing from Basement 1 upwards.
  5. Electrical work: wire pulling in progress at Level 19.
  6. Curtain wall installation ongoing at Level 8 and the south elevation from Level 4 to Level 9.
  7. Stair railings installation in progress from Ground Floor to Level 14.
  8. Level 10: sound insulation mats for floating floors and concrete pouring in progress
  9. Vertical firestopping at Level 4, and 5 ongoing.
  10. Horizontal fire sealant work from Level 7, 5, and 4 ongoing.