- 16th floor concrete pouring completed.
- 17th floor concrete slab pouring and forming ongoing.
- Structural vertical elements between L17 & L18 ongoing.
- Mechanical and HVAC work up to L09 ongoing.
- Electrical pulling wires on L14 ongoing.
- Curtain wall installation on L03, L04, and L05 ongoing.
- Escalators installation ongoing.
- Railing installation from B05 to B01M completed and GF to L09 ongoing.